Skema Pembiayaan Pembangunan MRT Fase III dan IV Dirancang Libatkan Swasta

Financing Scheme for MRT Phase 3 and 4 Construction Involves Private Sector

PT. MRT Jakarta (Perseroda) and the private sector have designed Phase 3 (East-West Line) and Phase 4. Of the total value, the private sector is targeted to absorb 40 percent of total financing.

Therefore, the East-West line and Phase 4 are sought from private funding of 40 percent

PT. MRT Jakarta President Director William P. Sabandar mentioned that in the initial phase, namely Phase 1 and 2, the entire development relied on financial support from the government. So far, JICA as the government's partner had committed to completing Phase 1 and 2 financings.

"We have a case study from England's Elizabeth Line where there is the involvement of the private sector. Therefore, the East-West line and Phase 4 are sought from private funding of 40 percent," he stated, Thursday (6/30).

Japan Commits to Boost Construction of Phase 2 MRT Jakarta

He explained that during a visit to England some time ago, his side also visited Crossrail International, which manages the Elizabeth Line in England. Elizabeth Line is a commuter line connecting the east and west of London.

He conveyed that the line construction was not all financed by the state. For example, the construction of stations and depots on the Elizabeth Line involves the private sector with the potential benefits offered.

The construction of Phase 3 (East-West Line) has a length of about 87 kilometers from Balaraja to Cikarang. He estimated that the construction budget to reach Rp 160 trillion.

Meanwhile, Phase 4 (Fatmawati-TMII) has a length of about 12 kilometers with an estimated budget of around Rp 22-30 trillion.

"In addition to England, we also visited France, Luxemburg, and South Korea, outside of Japan. The response has been very good," he said. the overall value, private sector is targeted to absorb up to 40 percent of total financing.

PT. MRT Jakarta President Director William P. Sabandar mentioned that in the initial phase, namely Phase 1 and 2, the entire development relied on financial support from the government. So far, JICA as the government's partner had committed to completing Phase 1 and 2 financings.

"We have a case study from England's Elizabeth Line where there is the involvement of the private sector. Therefore, the East-West line and Phase 4 are sought from private funding of 40 percent," he stated, Thursday (6/30).

He explained that during a visit to England some time ago, his side also visited Crossrail International, which manages the Elizabeth Line in England. Elizabeth Line is a commuter line connecting the east and west of London.

He conveyed that the line construction was not all financed by the state. For example, the construction of stations and depots on the Elizabeth Line involves the private sector with the potential benefits offered.

The construction of Phase 3 (East-West Line), he added, has a length of about 87 kilometers from Balaraja to Cikarang. He estimated that the construction budget to reach Rp 160 trillion.

Meanwhile, Phase 4 (Fatmawati-TMII) has a length of about 12 kilometers with an estimated budget of around Rp 22-30 trillion.

"In addition to England, we also visited France, Luxemburg, and South Korea, outside of Japan. The response has been very good," he said.

Linked News
Popular News indeks
  1. Jakarta to Hold Citywide Lights-Out Initiative

    access_time24-04-2026 remove_red_eye756 personAldi Geri Lumban Tobing
  2. Suckerfish Handling in South Jakarta is Run in Accordance with MUI Recommendations

    access_time21-04-2026 remove_red_eye650 personTiyo Surya Sakti
  3. Rano Leads Parking Arrangement on Jalan R.A. Kartini, Lebak Bulus

    access_time24-04-2026 remove_red_eye498 personBudhi Firmansyah Surapati
  4. Jakarta Residents Welcome Rp1 Public Transport Fare

    access_time24-04-2026 remove_red_eye497 personNurito
  5. PT JIEP Targets Shenzhen Businesses with Investment Offers

    access_time24-04-2026 remove_red_eye490 personAldi Geri Lumban Tobing